Core vs funded :

We’ve spent 12h on core last week. A few issues were discussed and Rachel will bring them as topic to the next finance circle :

  • Some project like the DFC orders are followed regarding time spend, and others regarding budget (which has a factor to count core funding, which hours count does not reveal)
  • Clockify shows amount in dollars: is this linked to the AU rate or can it be used to easily understand if there is money left
  • Delivery circle meeting hours are hard to attached to a dedicated budget. it’s unclear if we should all do that
  • how much is left on the Ubuntu project? Which instances have paid for the upgrades?
  • the first issues of a project have more budget room, so we should try to clarify most uncertainties with them (and of course reach an MVP that is usable in production)

Board

@dcook

  • Staging UK is now updated and can be used again :tada:
  • Found a workaround for Ansible, hoping this is enough to update all other servers

@Gaetan

  • Hoping the last product refactor will pass testing this week. @konrad will have a look
  • VINE app is in code review
  • Gaetan will move to checkout and perhaps have a look at the product preview bug

@maikel

  • Working on managing stock for the DFC / FDC projects. This might affect checkout (3 seconds slower) but UK pilots projects will show is this is a problem

Next up

We need estimate on :