Delivery circle 13th October

Topics

    • Variant tag release
    • Stripe upgrade
    • Node upgrade
    • 11th hour project
    • Quote for CoopCircuits on network 2.0 sourced variant
    • Payment webhook
    • Staging FR upgrade
    • Taler gem
    • Other tech debt upgrades

Current progress

  • Ahmed has everything to progress fixing s2 bugs and help the Stripe update / estimate OC UX update

  • Gaetan should be able to bring variant tags test ready this week and move to the node upgrade

  • Filipe will sync. with Gaetan on some question regarding the new tag page behavior. Testing the angular removal is a big piece. Rachel will look into it as well.

@dcook did lots of work last time. Do you have a view on this? Is that the best approach? I vaguely remember that you were wondering if a more gradual transition is possible.